Highlights
- Sunshine Silver announced completion of its 50,000-meter underground diamond drilling program on November 5, 2026.
- Third quarter 2026 net loss was $20,914 thousand, or $0.15 per share, compared with $9,875 thousand, or $0.09 per share.
- Cash and cash equivalents were $261,438 thousand at September 30, 2026, compared with $30,976 thousand at December 31, 2025.
- Sunshine plans a late 2028 mine restart, subject to a feasibility study expected in the second quarter of 2027.
Sunshine Silver Mining & Refining Company (NYSE:SSMR) shares were trading at USD 13.28 on November 17, 2026, up 4.78%, with a relative Volume at time of 6.34. The Idaho silver mine developer completed its initial public offering on June 5, 2026, announced the completion of its 50,000-meter underground drilling program on November 5 and filed its Form 10-Q for the quarter ended September 30, 2026 on November 12.
Sunshine Silver is a Delaware corporation with principal executive offices in Kellogg, Idaho. It owns and is developing the permitted Sunshine Mine, a past-producing silver mine in the Silver Valley of Idaho, along with the permitted Sunshine Silver/Copper Refinery one mile north of the mine, a tailings storage Facility and historical antimony refinery grounds. It reports one segment, exploration and pre-development, and it has not declared mineral reserves. Its fiscal year ends December 31.
Third Quarter Results
For the three months ended September 30, 2026, Sunshine Silver reported no sales, compared with $194 thousand a year earlier. Pre-development expense was $13,066 thousand, compared with $5,090 thousand, and general and administrative expense was $9,677 thousand, compared with $4,186 thousand. The operating loss was $23,361 thousand, compared with $9,726 thousand.
Interest income was $2,450 thousand, compared with $135 thousand. The net loss was $20,914 thousand, compared with $9,875 thousand, and the net loss per share was $0.15, compared with $0.09. For the nine months, the net loss was $50,886 thousand, or $0.40 per share, compared with $20,960 thousand, or $0.23 per share.
Infill Drilling and Pre-Development
On November 5, 2026, the company announced the completion of its 50,000-meter underground diamond drilling program. Drilling completed between April and October 2026 totaled approximately 33,898 meters across 144 holes. Results will inform the forthcoming updated mineral resource estimate and the Sunshine Mine Feasibility Study.
In the first nine months of 2026, the company completed approximately 1,835 meters of underground access expansion, including approximately 670 meters in the third quarter. It also advanced demolition of the existing mill.
Balance Sheet, Cash Flow and Capital
At September 30, 2026, total Assets were $314,397 thousand, total liabilities were $9,500 thousand and stockholders' Equity was $304,897 thousand. The accumulated Deficit was $255,463 thousand. As of November 12, 2026, the company had no long-term debt, and 143,940,693 shares of common stock were outstanding.
Net cash used in Operating Activities was $40,916 thousand for the nine months, and net cash provided by financing activities was $287,148 thousand. On June 5, 2026, the company closed its IPO of 23.0 million shares at $13.50 per share, including the full exercise of the underwriters' option to purchase 3,000,000 additional shares, for gross proceeds of approximately $310.5 million. The financial statements are prepared on a going-concern basis and note a history of operating losses and cash used in operations that are expected to continue until profitable operations commence. Management said available funds should be sufficient for at least twelve months.
Feasibility Studies and Outlook
The company plans to restart operations at the Sunshine Mine in late 2028, subject to the Sunshine Mine Feasibility Study and completion of mine and mill construction. It expects the study in the second quarter of 2027 and a final Investment decision after that. The new mill is designed to process up to 2,000 tonnes per day, compared with a current base case of approximately 1,000.
Feasibility studies for the Sunshine Silver/Copper Refinery and a potential Antimony Refinery are targeted for completion in the second quarter of 2027. The company said it may require additional funds at a later date and that there is no assurance they will be available on acceptable terms. It has not provided financial guidance.