Key Highlights
- Clean Vision's Subsidiary received an air quality permit for its Belle, West Virginia plant.
- The Belle site is a renovated building of about 60,000 square feet.
- Initial planned capacity is roughly 50 tons of plastic feedstock per day.
- State support includes a $1.75 million Loan from 2023 and a $15 million development loan.
Clean Vision Corporation (OTC:CLNV) has spent several years building toward commercial operation of a plastics pyrolysis plant in Belle, West Virginia, and the project now carries both a state air permit and public money. That combination raises a practical question for anyone following the OTC-quoted company: can it convert approvals and loans into a working Facility on a credible schedule?
Latest Company Context
On August 14, 2026, Clean Vision said its wholly owned subsidiary, Clean-Seas West Virginia (CSWV), had received its air quality permit from the West Virginia Department of Environmental Protection under application R13-3728. The Belle site is a renovated industrial building of about 60,000 square feet with initial planned capacity of roughly 50 tons of plastic feedstock per day. The company said next steps include equipment installation, commissioning, process optimization and workforce preparation.
Separately, Clean Vision filed a Form 15 to suspend its Section 15(d) reporting obligations, which were suspended by statute on January 1, 2026. Days after the permit, A media report on August 17 said the project is supported by a $1.75 million performance-based state loan from 2023, which carries employment requirements, and a $15 million high-impact development loan from the West Virginia Economic Development Authority approved in 2024.
Key Business and index Drivers
The central driver is execution. The same WVPB report quoted Tom Torres of the Ohio River Valley Institute, who cited the company's filings to argue that Clean Vision had announced at least 14 facilities in eight countries with only two operating, and that its accumulated Deficit exceeded $58 million at the end of 2025. Those are the critic's characterizations of company disclosures, but they highlight the funding gap a pre-revenue-scale project may face.
Torres also noted that the Belle opening, originally targeted for 2024, had slipped roughly six times; a September 2025 company release had pointed to fourth-quarter 2025 commissioning. A second pyrolysis unit, which he said represents about half of Belle's capacity, remains a key dependency. Earlier, the company said CSWV would receive a 25-ton-per-day reactor and that it had retired a convertible note. Broader acceptance of chemical recycling, feedstock Supply from the Mid-Atlantic region and offtake pricing for pyrolysis oil may also shape results.
What Investors Should Watch
Investors may watch for company announcements on equipment installation and commissioning at Belle, since the permit removes one obstacle but not the engineering and funding work that remains. Any disclosure of financing for the second reactor, or of progress against the employment conditions attached to the state loan, could indicate whether the project timeline is firming. Because Clean Vision has suspended SEC reporting, investors may also check OTC Markets for any voluntary financial disclosures, which could be the main source of updated figures on cash, Debt and losses. Community and environmental group commentary on pyrolysis in West Virginia may continue, and any regulatory follow-up on the permit could be relevant. No specific dates for commissioning or first commercial output have been confirmed.
Permits Granted, Delivery Pending
Clean Vision now holds the key air permit for its first U.S. Plastic Conversion Network hub, and the project has drawn meaningful state lending support. At the same time, a history of delays, a large accumulated deficit cited by critics and reduced SEC disclosure leave important questions open. Whether the Belle plant reaches commissioning and steady throughput could be the clearest test of the business model, and investors may weigh verified operating milestones more heavily than announcements as the project moves forward.