Key Highlights
- Microsoft pulled out of a deal to anchor Nscale’s Loughton data center in Essex after power connection delays.
- Electricity grid officials do not expect to supply power to the Loughton site until the 2030s.
- Microsoft said the decision relates to a single site, and both companies say their wider partnership remains in place.
- Grid queues delay data center projects by up to 13 years, and Nscale has filed for a US IPO.
The Withdrawal
Microsoft (NASDAQ:MSFT) has pulled out of a deal to anchor a flagship data center for Nscale, a company backed by Nvidia (NASDAQ:NVDA). Power connection delays pushed the expected supply date into the 2030s, highlighting a major obstacle to Britain’s AI ambitions.
The US tech giant said on Monday it remained committed to its partnership with Nscale, including work to build digital infrastructure and support AI growth globally.
“This decision relates to a single site,” a Microsoft spokesperson said of its termination of the agreement for the data center in Loughton, Essex. Nscale had faced delays there, with electricity grid officials informing the AI company they did not expect to supply power to the site until the 2030s.
Nscale’s Response
“Our relationship with Microsoft remains strong and long-term, and this unfortunate London-wide grid issue has no impact on our other contracts,” a spokesperson for Nscale said. The spokesperson added: “We remain committed to both the Loughton project and the UK, and we are exploring alternative power sources for the site, as well as other expansion sites in the UK.”
What Was Planned
The Loughton site was due to begin operating early next year, with 23,040 Nvidia GB300 GPUs providing 50 megawatts of AI computing capacity to help power Microsoft’s Azure services in Britain, the companies said last year.
The project was among technology deals announced during US President Donald Trump’s visit to Britain in September 2025, which were intended to showcase the country’s ambition to become a global AI leader. A month later Nscale expanded its Microsoft relationship to about 200,000 GB300 GPUs across sites in Texas, Portugal, Norway and Loughton, where more than 23,000 were planned.
The Grid Bottleneck
That ambition faces a major constraint in the form of electricity supply. Bottlenecks in grid connection queues are delaying data center projects by as long as 13 years. Nscale described the Loughton project in 2025 as the largest AI data center in the country, and its spokesperson now calls the cause a London-wide grid issue.
Nscale’s Rapid Growth
Nscale filed for an initial public offering in the United States last month, proposing a New York Stock Exchange listing, and its prospectus names Microsoft and Anthropic among its major customers. The company has not disclosed how many shares it sells or a price range. As of August 31 it had about 461,000 active or contracted GPUs, and the Anthropic agreements are tied to a compute campus in West Virginia. Its agreements with Microsoft provide for payments of up to USD 43.8 billion, and those with Anthropic provide for up to approximately USD 44.6 billion. Together the two customers account for roughly USD 88 billion of the USD 103 billion in contracted value.
The group provides infrastructure, including computing capacity, power and data centers, as well as software for training and running AI models. It has grown rapidly since launch, increasing its total contracted value from USD 100 million to more than USD 103 billion in two and a half years.
The filing shows revenue of USD 140.6 million in the first six months of 2026, up from USD 10.4 million a year earlier, and a net loss of USD 1.02 billion over the same period. One customer accounted for 52 percent of first-half revenue.
Nscale competes with AI infrastructure providers CoreWeave (NASDAQ:CRWV), Nebius (NASDAQ:NBIS), Crusoe and Lambda.