Key Highlights

  • Finland's licensing and supervision agency ordered Google's local unit to halt work at two Data Center sites by Oct. 23.
  • The suspension stays in place until environmental impact assessments are completed for the Muhos and Kajaani projects.
  • The order lands one month after Google committed USD 15 billion to AI infrastructure in Finland, its largest European investment.
  • A Google spokesperson said the company had "fallen short of our own high standards in this instance."

The Suspension Order and Its Background

Finland's Licensing and Supervision Agency, known as LVV, has told Google to stop building work on two planned data centers until environmental impact assessments are finished. The notice went on Tuesday to Tuike Finland Oy, a Google subsidiary, and covers the sites at Muhos and Kajaani. Work must stop no later than Oct. 23.

The order applies to tree removal, topsoil removal, excavation, quarrying, crushing, moving of soil masses, ditching, and the construction of roads and storage areas. Planning, measurements, soil surveys and other low-impact measures that can easily be reversed are not covered.

Tommi Muilu, head of the agency's environmental department, said the measures in question "will change the environment and cause impacts, the identification and assessment of which are among the key objectives of the EIA procedure."

A Google spokesperson said the company understood the concerns and had "fallen short of our own high standards in this instance," adding that it would follow the agency's guidance. The spokesperson said the company had acted in good faith under the Forestry Act, run nature surveys and put protections in place for high-value areas. Landscaping and biodiversity plans include tree planting across 130 hectares (320 acres) at Muhos.

Finnish press reports describe tree felling of about 330 hectares at Muhos, carried out by Google's contractor without an environmental impact assessment. Finnish law requires one for contiguous felling above 200 hectares where trees are removed permanently. The felling began in March 2026 and continued until August, and the agency is examining whether the contractor's actions were lawful. Google's contractor has said the cleared area at Kajaani is under 200 hectares, which falls below the threshold. Nature conservation groups have pressed the agency to use enforcement powers, and one said four sites that the plans described as protected had already been flattened.

Finland's Pull for Data Centers

Finland has become a prominent location for data centers during the AI boom. Hyperscalers and developers have targeted its available land and power, which are scarce across much of Europe, and several projects with potential capacities of hundreds of megawatts have been announced. The Demand has earned the country the nickname "Texas of Europe," a reference to the U.S. state that hosts some of the largest AI data center projects in the world.

Google's plan for Finland, announced about a month ago, is its largest Investment in Europe. The company put the commitment at USD 15 billion, or at least EUR 13 billion, deployed through 2028 into data centers and supporting projects such as energy. It has said the work covers data centers, grid improvements and clean energy and battery projects. Google has said the work would support roughly 7,000 jobs a year once operational and add about USD 3.6 billion to Finland's GDP during construction. Finland's Prime Minister Petteri Orpo called the decision "a clear testament to our strengths."

Permitting Steps and Site Milestones

Two dates frame the next stage: the Oct. 23 deadline for work to stop and the completion of the environmental impact assessments, which set when the suspended activities can resume. The agency's review of the Muhos felling, and the status of the Kajaani site against the 200-hectare threshold, are the other points that bear on both projects.