Key Highlights

  • Third quarter 2026 Revenue rose to USD 1.96 million from USD 1.74 million, with oil revenue of USD 1.81 million, and net loss was USD 3.5 million, or USD 0.07 per share, against USD 3.3 million, or USD 0.10.
  • Lease Operating Expense was USD 2.1 million against USD 1.0 million, including about USD 1.2 million of remediation costs after a release of produced fluids from a legacy gathering line.
  • The company holds a five-year helium offtake at a fixed USD 285 per Mcf for 1.2 million cubic feet a month, and management targets first production in spring 2027.
  • Cash was USD 2.9 million and total Liquidity was USD 14.4 million on September 30, 2026, including USD 11.5 million of undrawn capacity under a USD 20 million borrowing base facility.

Oil Revenue Edges Up While Remediation Costs Deepen the Loss

Big Sky Industrial (NASDAQ:BSIN) filed its Quarterly Report on November 10, 2026 and held its call on November 11. Revenue was USD 1.96 million against USD 1.74 million, as management said a 30% rise in average realized price to USD 63.83 per Barrel of Oil Equivalent outweighed lower volumes after a 2025 asset sale. Production was 30,628 barrels of oil equivalent, 76% oil. The company holds a low-decline Montana Oil Field and is building an industrial gas business. Lease operating expense doubled to USD 2.1 million on remediation of the pipeline release. General and administrative expense was USD 2.2 million, and the net loss was USD 3.5 million (GAAP).

Helium Contract, Plant Timeline and the Pending EPA Approval

Management said Phase 1 field work is complete, long-lead generators are on site and modular plant fabrication is underway, with first production targeted for spring 2027. The plant is designed for more than 14 million cubic feet of helium and about 125,000 metric tons of CO2 captured a year. At the contract Volume and price, calculated annual helium sales would be roughly USD 4.1 million, since 1,200 Mcf a month at USD 285 is about USD 342,000 a month. The EPA review of its Big Rose CO2 monitoring plan, submitted October 9, 2025, is in its final stage, and management said approval is not required to start the plant but sets when 45Q credits begin.

Liquidity, Financing Talks and Phase 2 Ambitions

Cash was USD 2.9 million, up from USD 0.4 million at the end of 2025, and the Credit Facility balance was USD 8.5 million against USD 2.5 million. The facility matures in May 2029 and has no covenant testing through the quarter ending March 31, 2027. Management said it is negotiating a larger senior secured facility and discussing the sale of Phase 1 45Q credits. It expects to recover up to USD 1.0 million of cleanup costs under a Liability policy, though no receivable was booked. Unproved industrial gas properties rose to USD 42.5 million. A Phase 2 Investment decision is expected in the coming months, subject to financing and sizing.

Where Things Stand

The contract answers revenue visibility, not near-term cash burn. Big Sky Industrial (NASDAQ:BSIN) has a fixed USD 285 per Mcf price on a five-year take-or-pay offtake with an investment-grade buyer, according to management, yet the plant is not yet built and the quarterly net loss was USD 3.5 million. Funding rests on a credit facility with USD 11.5 million undrawn, a possible larger facility and 45Q credit sales. Next markers are the EPA decision, civil work and equipment installation, financing announcements, a Phase 2 decision and first production in spring 2027.