Key Highlights
- Sempra (NYSE:SRE) reported Q2 2026 adjusted EPS of $1.16, beating the $1.01 estimate by 14.85 percent.
- The company affirmed full-year 2026 adjusted EPS guidance of $4.80 to $5.30 and 2027 EPS growth of 7 to 9 percent.
- Sempra's record $65 billion five-year capital plan is increasingly weighted toward Sempra Texas, targeting over 60 percent of the total base by 2030.
- ECA LNG Phase 1 faces a delay to Q4 2026 due to equipment damage discovered during maintenance.
Higher Equity Earnings at Texas and California Drive the Beat
Sempra (NYSE:SRE), a San Diego-based energy infrastructure company operating regulated utilities and infrastructure assets across North America, reported second quarter GAAP earnings of $796 million, or $1.21 per share, up from $461 million, or $0.71 per share, in the year-ago quarter. Adjusted earnings were $762 million, or $1.16 per share, up from $583 million, or $0.89 per share, a year earlier, driven by higher equity earnings at Sempra Texas and California, and lower equity losses at Sempra Infrastructure.
The company affirmed full-year 2026 adjusted EPS guidance of $4.80 to $5.30 and reiterated 2027 EPS growth expectations of 7 to 9 percent, with its record $65 billion five-year capital plan increasingly weighted toward Sempra Texas, targeting over 60 percent of the total capital base by 2030.
Oncor's Expanding Capital Opportunity Set Against an LNG Project Delay
Oncor is executing a $47.5 billion five-year capital plan with $10 billion of incremental capital opportunities, and management expressed growing confidence in this incremental batch process, representing further upside beyond the peak load already identified with ERCOT's batch process, with an update expected alongside the company's Q4 earnings call and investor day in 2027.
Sempra Infrastructure's ECA LNG Phase 1 project faces a delay due to equipment damage discovered during maintenance, with substantial completion now expected in the fourth quarter of 2026 and sales under long-term agreements set to begin shortly after; Port Arthur LNG Phase 1 and 2 remain on time and on budget. The pending KKR/Sempra Infrastructure Partners transaction, involving a 45 percent equity stake sale, is expected to close later in the third quarter and would deconsolidate over $9 billion of debt from the company's balance sheet, a significant balance sheet benefit.
Balancing Texas Growth Momentum Against LNG Execution Risk
The growing weight of Sempra Texas within the company's overall capital plan, combined with Oncor's expanding incremental capital opportunity, suggests the company's regulated transmission and distribution business is emerging as an increasingly dominant driver of long-term growth. Should the additional $10 billion in incremental Oncor capital opportunities materialize as management anticipates, this could provide further upside to the company's already substantial five-year plan.
However, the ECA LNG Phase 1 delay introduces near-term execution uncertainty for Sempra Infrastructure, even as Port Arthur LNG's phases remain on schedule. The pending transaction with KKR and Sempra Infrastructure Partners, if it closes as expected in the third quarter, would meaningfully improve the company's balance sheet by deconsolidating a substantial amount of debt, providing additional financial flexibility.
Conclusion
Sempra's second quarter results reflect strong earnings growth driven by its regulated Texas and California utility operations, even as its LNG infrastructure segment navigates a project delay at ECA LNG Phase 1. Whether the company's growing emphasis on Sempra Texas and Oncor's expanding capital plan continues to drive long-term earnings growth may depend on regulatory outcomes tied to Texas transmission approval processes and California wildfire liability legislation. The pending KKR transaction and its associated debt deconsolidation could provide a meaningful balance sheet improvement once finalized.