Net Power Inc. filed a Form 8-K on November 23, 2026, disclosing that its subsidiary Net Power, LLC and Saulsbury Industries, Inc. executed Amendment No. 2 to the Agreement to Extend FNTP Date on November 22, 2026, pushing a key EPC milestone deadline from November 20, 2026 to December 4, 2026.
Key Highlights
- Deadline extended: The date by which the Fourth Amendment and the Limited Notice to Proceed (LNTP) must be executed was extended from November 20, 2026 to December 4, 2026.
- Termination payment deferred: The $3.5 million termination payment under the Extension Agreement remains deferred, provided the Fourth Amendment and LNTP are executed and required payments made by December 4, 2026.
- Saulsbury confirmation: In Amendment No. 2, Saulsbury confirmed that it has not demanded the Termination Payment, that the Termination Payment is not payable, and that it remains deferred.
- Customer approval: On November 20, 2026, the prospective customer under the Cost Reimbursement Agreement approved Amendment No. 2 and the form of the Fourth Amendment, subject to changes that do not increase the requested amounts or make the documents materially less favorable to the prospective customer.
- No binding offtake agreement: The company disclosed that it has not entered into a binding energy services or power offtake agreement for the Initial Project, and the prospective customer is not obligated to enter into one.
Net Power and Saulsbury Amend EPC Extension Agreement for Initial Project
According to the filing, Net Power, LLC, an indirect subsidiary of NET Power Inc. (NYSE:NPWR), and Saulsbury Industries, Inc. entered into Amendment No. 2 to the Agreement to Extend FNTP Date on November 22, 2026. The amendment modifies the Extension Agreement, which had been effective as of October 15, 2026 and previously amended, by replacing references to the November 20, 2026 deadline with December 4, 2026. All other terms of the Extension Agreement remain unchanged, the company disclosed.
The filing explains that the Purchaser and Saulsbury are negotiating a post-closing change order to the Engineering, Procurement and Construction Agreement dated December 15, 2025 (the "EPC Agreement"), referred to as the Fourth Amendment, along with a Limited Notice to Proceed (LNTP). Net Power, LLC acquired its position under the EPC Agreement on August 31, 2026, when it assumed the role previously held by EMPower USA, LLC. The $3.5 million termination payment that would otherwise be owed under the Extension Agreement will remain deferred so long as the Fourth Amendment and LNTP are executed and the payments required under the LNTP are made by December 4, 2026, according to the filing.
The company also noted that there is "an absence of any committed equipment or project-level financing, customer funding or partner capital other than the conditional Cost Reimbursement Agreement" and no final investment decision has been made. The company stated that it intends to file the full text of Amendment No. 2 as an exhibit to its Annual Report on Form 10-K. The filing contains forward-looking statements that are the company's own and subject to its cautionary language regarding risks and uncertainties.
What Was Disclosed
NET Power Inc. disclosed the execution of Amendment No. 2 extending an EPC-related milestone deadline to December 4, 2026, the continued deferral of a $3.5 million termination payment, Saulsbury's confirmation that the payment has not been demanded, and the absence of a binding offtake agreement for the Initial Project.