enCore Energy Corp. announced on November 19, 2026, that the Texas Commission on Environmental Quality has issued the Production Area Authorization for the first wellfield at the company's Upper Spring Creek In-Situ Recovery Uranium Project in South Texas.

Key Highlights

  • Authorization received: TCEQ issued PAA-1 for the first wellfield at the Upper Spring Creek project within the company's previously disclosed timeline.
  • Extraction targeted for early December: The company reported it is making final inspections and expects oxygenated water injection and uranium extraction to begin the first week of December.
  • One regulatory step remaining: Final approval to operate the Waste Disposal Well (WDW-467) at Upper Spring Creek is pending, with TCEQ approval expected in December.
  • Largest satellite facility built to date: According to the filing, USC is described as "the largest satellite facility the Company has built to date."
  • Processing route confirmed: Uranium-loaded resin from the Satellite Ion Exchange Plant will be trucked to the Rosita CPP for processing into yellowcake.
  • Project acquisition history: The company acquired the Upper Spring Creek project in December 2020; it was previously held by Signal Equities LLC.

Upper Spring Creek Wellfield Authorization and Path to Full-Scale Operations

enCore Energy Corp. (NASDAQ:EU; TSXV: EU) disclosed that TCEQ has issued PAA-1 for the Upper Spring Creek ISR Uranium Project, authorizing uranium extraction within the first defined wellfield area. According to the filing, PAA-1 is described as "the final wellfield permit required for injection and recovery." The Satellite Ion Exchange Plant and the first wellfield were constructed ahead of receiving the authorization.

The filing explains that ISR operations recover slightly more solution from a wellfield than is injected in order to keep wellfield solutions contained. This excess saline water, referred to as the bleed stream, is disposed of through a permitted deep disposal well. The Waste Disposal Well at Upper Spring Creek has been fully constructed, and TCEQ approval to operate it is identified as the remaining step before the wellfield can be brought to its designed operating rates. The company stated it expects to receive that approval in December and will update the market when the wellfield moves to full-scale operations.

Rich Little, Chief Executive Officer, was quoted in the filing: "The plant and wellfield are built and ready, and our team is focused on completing the last regulatory step. Once the Waste Disposal Well is approved, we expect to bring the wellfield up to full-scale operations and begin delivering the growth in extraction that our South Texas investments were designed to provide." The filing also notes that the uranium-mineralized sands at the project lie within the Oakville Formation at depths typically between 300 and 450 feet below surface. Technical disclosure in the release was reviewed and approved by Dain McCoig, P.E., MBA, enCore's Chief Operating Officer, identified as a Qualified Person under Canadian National Instrument 43-101 and S-K 1300.

What Was Disclosed

enCore Energy disclosed receipt of the PAA-1 wellfield authorization from TCEQ for its Upper Spring Creek ISR Uranium Project in South Texas, with uranium extraction targeted to begin the first week of December pending final approval of the on-site Waste Disposal Well.