AGCO Corporation announced on November 19, 2026, that Project Olmedo, the solar installation at the center of its first Virtual Power Purchase Agreement with BRUC, has completed construction and commissioning in Valladolid province, Spain.

Key Highlights

  • Construction complete: Project Olmedo has finished construction and commissioning, with renewable electricity delivery to Spain's grid pending final regulatory approvals.
  • Scale of the installation: The two solar projects, Los Silos and El Granero, span approximately 300 hectares (741 acres) and hold approximately 150,000 solar panels.
  • Expected output: AGCO's portion of annual production is expected to be approximately 150 gigawatt-hours (GWh) of renewable electricity per year.
  • 10-year agreement: The VPPA with BRUC was announced in September 2025 and runs for 10 years.
  • Emissions goal: The agreement supports AGCO's commitment to reduce absolute Scope 1 and 2 emissions by 55% by 2033 from a 2022 baseline.
  • Agricultural land use: Local farmers lease land for the project while retaining the option for livestock to graze among the panels.

AGCO's First VPPA Reaches a Construction Milestone in Valladolid

According to the filing, AGCO (NYSE:AGCO) announced that Project Olmedo, built by BRUC in the northwest Spanish province of Valladolid, has completed construction and commissioning. The installation is expected to begin delivering renewable electricity to Spain's power grid in the coming months, subject to final regulatory approvals. BRUC is described in the filing as one of the largest renewable energy groups in Spain. AGCO and BRUC leaders, along with local officials, held a ribbon-cutting ceremony at the site on November 3.

The filing explains that a Virtual Power Purchase Agreement allows a company to support new renewable energy projects without taking direct delivery of the electricity generated. Because AGCO's agreement funded construction of a brand-new installation, it adds new renewable capacity to the grid rather than drawing on existing sources, a principle the filing identifies as "additionality." Technical advisory support was provided by Schneider Electric, and the filing states the project required more than two years of involvement across multiple AGCO teams and functions.

AGCO is described in the filing as a global leader in agricultural machinery and precision agriculture technologies, operating under brands including Fendt, Massey Ferguson, PTx, and Valtra. The company's supply chain chief, Tim Millwood, Senior Vice President and Chief Supply Chain Officer, stated in the filing that the agreement provides "long-term price certainty for the majority of the electricity certificate cost in Europe" over a 10-year period. AGCO's portion of Project Olmedo's annual output is expected to be approximately 150 GWh, which the filing says is equivalent to the annual electricity consumption of approximately 40,000 European households based on Eurostat data. The agreement is intended to reduce Scope 2 greenhouse gas emissions from purchased electricity in AGCO's Europe/Middle East region.

What Was Disclosed

AGCO disclosed the completion of construction and commissioning of Project Olmedo, a two-site solar installation in Spain built under a 10-year VPPA with BRUC, covering approximately 741 acres, 150,000 solar panels, and an expected annual output of approximately 150 GWh for AGCO's portion.