Key Highlights
- Applied Digital leased 150 megawatts to an unnamed investment-grade hyperscaler, worth USD 5.4 billion over an 18-year base term.
- The Lease can extend to 33 years, worth about USD 12.7 billion if the tenant exercises all renewal options.
- Contracted base-term lease Revenue now exceeds USD 41 billion, with about 75% tied to investment-grade customers.
- Delivery is scheduled to begin in the first half of 2028, subject to milestones, Utility arrangements and approvals.
Another Hyperscaler Lease, With Better Terms
Applied Digital (NASDAQ:APLD) said on Monday, Nov. 23, that it has leased 150 megawatts of critical IT capacity to an investment-grade hyperscaler, a deal that carries USD 5.4 billion in contracted revenue over a base term of 18 years. The company did not name the tenant. It said the lease carries improved commercial terms compared with its prior leases, including higher pricing.
The agreement follows a 15-year, 210 megawatt lease worth about USD 5.2 billion that the company signed in June at its Delta Forge 2 site.
Lease Terms at a Glance
- Capacity: 150 megawatts of critical IT load.
- Base term: 18 years, with contracted revenue of USD 5.4 billion.
- Renewals: The tenant can extend to a total of 33 years, bringing the deal to about USD 12.7 billion if all Options are exercised.
- Tenant: An unnamed investment-grade hyperscaler.
- Delivery: Capacity is scheduled to begin delivery in the first half of 2028, subject to development milestones, utility arrangements and regulatory approvals.
How the Pricing Compares With Earlier Leases
Dividing contract value by capacity and term gives a rough measure of price. The new lease works out to about USD 2.0 million per megawatt per year (USD 5.4 billion over 150 megawatts and 18 years). Earlier leases, according to the company's announcements, imply lower figures:
- October 2025, Polaris Forge 2: about USD 5 billion for 200 megawatts over 15 years, or roughly USD 1.7 million per megawatt per year.
- April 2026, Delta Forge 1: about USD 7.5 billion for 300 megawatts over 15 years, also roughly USD 1.7 million.
- May 2026, Polaris Forge 3: about USD 7.5 billion for 300 megawatts over 15 years, again roughly USD 1.7 million.
- June 2026, Delta Forge 2: about USD 5.2 billion for 210 megawatts over 15 years, or roughly USD 1.65 million.
On that rough arithmetic, the new lease is priced about 20% above the April deal, which fits the company's statement about higher pricing. The calculation excludes escalators, renewal options and any differences in what each tenant receives, so it indicates direction and not exact terms.
Financing the Build
The chief financial officer said the company plans to finance the build through its established structure, citing a USD 5 billion Equity Partnership with Macquarie Asset Management, followed by project financing. The structure matters because the company carries substantial debt. In its fiscal first quarter ended Aug. 31, it reported revenue of USD 341.9 million, up 322% from a year earlier, while Debt totaled USD 6.4 billion against USD 3.7 billion in cash, cash equivalents and restricted cash.
A Larger, More Concentrated Backlog
Applied Digital said its total contracted base-term lease revenue now exceeds USD 41 billion, or about USD 100 billion if all renewals are counted, and that about 75% of the base-term total is tied to investment-grade customers. The base-term figure compares with about USD 36 billion reported in October and more than USD 23 billion after the April lease, so the new deal fits the pace at which the Backlog has grown. A tenant with an investment-grade Credit rating lowers payment risk for lenders, which is why the share of the backlog tied to such customers bears on how easily projects can be financed.
On the delivery side, the company reported about 1.41 gigawatts of leased critical IT load across five campuses in October, with 250 megawatts live at its Polaris Forge 1 campus after a second 75 megawatt phase became operational on Oct. 1. The new lease adds capacity that is contracted but not yet built, which keeps development and financing execution at the center of the story.
Share reactions to earlier lease announcements have varied. The stock gained about 12% after the April Delta Forge 1 lease and fell almost 8% after the October 2025 announcement, a reminder that investors weigh price, financing and timing and not only headline value.
What Would Show the Lease Converting to Revenue
The lease is contracted revenue, not recognized revenue, and delivery is scheduled to begin in the first half of 2028. Markers to follow include progress on the development milestones, utility arrangements and regulatory approvals named as conditions, the close of the Macquarie equity partnership and the project financing behind this build, and whether total debt rises from the USD 6.4 billion reported in the fiscal first quarter. Disclosure of the tenant, or of how this lease is allocated across the company's campuses, would add detail the announcement leaves out. Whether the next lease announcement again lists higher pricing than the one before, and whether the investment-grade share of the backlog rises from about 75%, would show if the improvement is a trend. The next Quarterly Report would show how much of the backlog is moving from contract to capacity.