Key Highlights

  • Boeing is carrying a record Backlog of more than 6,300 unfilled orders for commercial aircraft.
  • The US aerospace and defense sector booked Revenue of almost USD 1 trillion in 2025.
  • Data center builders compete for steel, electrical switches, cooling systems and the contractors who install them.
  • Defense firms are struggling to meet Pentagon demands for higher munitions output amid two conflicts.

The race to build data centers for artificial intelligence is colliding with another American industrial priority. Aerospace and defense manufacturers say they are finding it harder to secure the workers and production capacity they need.

The chief executive of the US Aerospace Industries Association, which represents major contractors and suppliers, said spending by large cloud companies was draining workforce, land and energy while raising Supply costs. Technology firms, in his view, have such deep pockets that competition has intensified for an industry already stretched.

A Backlog With No Slack

Boeing (NYSE:BA) illustrates the strain. The company has more than 6,300 unfilled orders for commercial aircraft, a record.

Chief executive Kelly Ortberg acknowledged last month that its recovery plan had slipped at least a year behind schedule. He cited rising costs, difficulties with wing production and a series of supply chain problems.

Defense Demand adds to the load. Leading contractors are struggling to meet Pentagon requests to raise munitions output amid the conflicts in Ukraine and the Middle East.

Competing for the Same Parts

The overlap goes deeper than obvious items. An aerospace and defense analyst at a large US bank said cloud companies draw on much of the same supply chain, from turbine blades and castings to printed circuit boards and electronic components.

Memory chips show the effect. Their prices have climbed sharply in recent years because of AI demand, and cutting-edge production has drawn capacity away from the older chips that aerospace and defense equipment still uses.

Squeezed Out of Construction

Even companies willing to spend heavily on new plants can lose the contest for builders. A representative of an engineering and construction firm said aerospace and defense groups investing in large facilities had been squeezed out by Data Center developers.

The competition covers steel, electrical switches and climate control systems, along with the contractors who put them together. These are basic ingredients of any modern factory, so a shortage can delay a project long before its first product is made.

Small Volumes, Little Leverage

Despite revenue of almost USD 1 trillion in 2025, the industry buys in relatively small quantities. The association's chief executive contrasted it with consumer electronics, data centers and automakers, whose volumes are large enough to shape supplier markets.

Moving production of critical inputs back to the United States would raise costs further, he argued. For decades the sector relied on single suppliers for thousands of components to save money, leaving few alternatives when one of them is overwhelmed.

Those suppliers now face commercial and military demand at once. They are also contending with high Inflation and with skills shortages that worsened during the Pandemic and have deepened with the data center build-out.

Caution Down the Chain

Smaller firms are the weak point. A single missing part can hold up a finished aircraft or weapon, so the capacity of a modest supplier can set the pace for a far larger manufacturer. An executive at a Texas-based component distributor said the industry had underestimated the pressure on them and the difficulty of investing ahead of demand.

History makes suppliers wary. An analyst at a research firm said that when manufacturers set targets that prove too optimistic, some suppliers discount them and hold back on hiring and materials, having seen both Boeing and Airbus miss goals before.

The bank analyst said Boeing's original plan to raise 737 production by five aircraft a month every six months had never been realistic. Its newer and more conservative schedule, the research analyst added, helps explain suppliers' reluctance to build extra capacity. Boeing, asked about the strain, pointed to the association chief's comments.

Backlogs Cut Two Ways

Long waiting lists frustrate customers, particularly airlines seeking more fuel-efficient jets at a time of expensive fuel. For manufacturers they are not necessarily a problem, since a large order book provides years of visible work. The bank analyst put it simply, noting that companies get into trouble by building too many aircraft rather than too few.

Where the Pressure Could Ease

The strain depends partly on forces outside the industry's control. If Investment in data centers slows, as some investors now fear it might, competition for contractors, components and workers would ease. If spending continues at the current pace, aerospace and defense firms may need longer contracts, closer support for suppliers or government help to secure capacity.

For governments, the issue is whether defense production can rise as quickly as security plans assume. For airlines, it is how soon ordered aircraft arrive. Delivery schedules, supplier investment and progress on 737 output would offer the clearest signals of whether the industry is regaining ground or falling further behind its commitments. None of these measures moves quickly, because a new factory, a trained machinist or a qualified supplier takes years to put in place, and a data center project nearby can claim any of them first.