Key Highlights
- EPS of USD 1.06 came in below the USD 1.12 consensus estimate, while GAAP diluted EPS rose to USD 1.00.
- Revenues of USD 971 million rose 2% from USD 952 million but trailed the consensus estimate of USD 1.02 billion.
- Net income increased 16% to USD 119 million as administrative and other costs fell USD 13 million.
- Industrial retail Revenue climbed to USD 177 million from USD 141 million while residential slipped to USD 362 million.
Portland General Electric Company (NYSE:POR) reported third quarter 2026 Earnings Per Share of USD 1.06, below a consensus estimate of USD 1.12. The quarterly filing shows GAAP diluted EPS of USD 1.00 compared with USD 0.94 a year earlier. Total revenues were USD 971 million, up from USD 952 million but under the consensus estimate of USD 1.02 billion. Net Income rose to USD 119 million from USD 103 million, and income from operations reached USD 187 million versus USD 174 million.
Industrial Demand and Cost Lines Behind the Quarter
Retail revenues of USD 809 million rose USD 15 million, helped by regulatory deferral recoveries built into 2026 customer prices, while lower retail energy deliveries subtracted USD 14 million. Total retail deliveries fell 3.0%, or rose 0.7% on a weather adjusted basis, with industrial deliveries up 6.0%. Wholesale revenues grew 5% to USD 143 million on higher prices despite a 13% drop in sales volume.
Purchased power and fuel expense rose to USD 383 million from USD 372 million as the average variable power cost climbed to USD 47.44 per MWh from USD 44.92. Administrative and other expense fell to USD 86 million from USD 99 million, and the quarter included USD 9 million of Business transformation and optimization expense. Net interest expense edged up to USD 62 million on higher Debt balances, and taxes other than income taxes rose 15% to USD 54 million.
Washington Acquisition and Capital Plan
Portland General agreed in February 2026 to buy select Washington generation, transmission and Utility operations from PacifiCorp for USD 1.9 billion, adding about 140,000 customers. The package includes the Chehalis thermal plant at 477 MW, the Goodnoe Hills wind Facility at 94 MW and the Marengo I and II wind facilities at 234 MW. The company submitted a FERC application in July requesting a decision by December 15, 2026, and the financing plan includes up to USD 600 million of Equity from a joint venture partner.
Estimated capital expenditures are USD 1.57 billion for 2026 and USD 1.65 billion for 2027, excluding AFUDC. Cash from operations for 2026 is projected at USD 950 million to USD 1.15 billion, with up to USD 700 million of Long Term Debt issuance. Total Liquidity stood at USD 1.00 billion at quarter end, and nine month proceeds from equity forward sales were USD 156 million.
Regulatory and Procurement Signposts
The next filings and decisions are tied to dates and megawatts. The FERC decision request of December 15, 2026 is one marker, and the company projects closing the Washington deal about twelve months after regulatory applications filed in March and April 2026. A 2026 resource plan submitted on October 15 identifies a need of about 3,400 MW by 2030 under one pathway and about 6,700 MW under another.
Procurement milestones also stand out. In October the company signed a build transfer agreement for Biglow Optimization Phase 2, a 200 MW solar and 250 MW battery project at roughly USD 900 million, and the Salmonfly project at about USD 853 million remains subject to Oregon commission process. The company noted that its 2025 request for proposals is delivering fewer viable projects than first anticipated. Forecast net variable power costs sit within the deadband, so no 2026 customer refund is projected.