Key Highlights
- Revenue of USD 1.96 million beat the USD 1.78 million estimate, up 12%; the loss was USD 0.07 per share.
- The average realized price rose 30% to USD 63.83 per BOE, more than offsetting lower volumes after a 2025 divestiture.
- Lease Operating Expense was USD 2.1 million, including about USD 1.2 million of remediation costs from a produced fluids release.
- Cash was USD 2.9 million, with USD 11.5 million of Credit Facility availability and USD 17.2 million raised from equity.
Big Sky Industrial Inc. (NASDAQ:BSIN), an oil and gas producer developing a helium project, reported third quarter 2026 Revenue of USD 1.96 million, above the USD 1.78 million estimate and up 12% from USD 1.7 million. The loss of USD 0.07 per share was wider than the USD 0.04 estimated loss.
Management said a 30% increase in average realized price to USD 63.83 per BOE more than offset lower volumes following the 2025 divestiture of its Wyoming and West Texas properties, which carried higher operating costs. The filing shows nine-month net loss of USD 9.0 million.
Operating Costs and Remediation
Lease operating expense was USD 2.1 million against USD 1.0 million, which management attributed to about USD 1.2 million of remediation and related costs from a previously disclosed release of produced fluids from a gathering line in its legacy oil operations. Excluding these costs, Lease operating expense was USD 0.9 million, or USD 29.71 per BOE, against USD 29.58 a year earlier.
Management said it submitted a claim under its general Liability policy, which provides USD 1 million of coverage for pollution cleanup costs after a USD 100,000 deductible, and that it expects to recover up to USD 1 million. Cash general and administrative expense was USD 1.6 million against USD 1.7 million, which management attributed to lower accounting and tax professional fees.
Helium Phase 1 and Liquidity
Management said every structural piece of Phase 1 was in place in August, including engineering, permitting, EPC, funding and offtake, and that what remains before first revenue is execution. It said EPA approval of the monitoring, reporting and verification plan has taken longer than hoped, noting such approvals historically have taken 12 months or longer, and that the approval is not a condition to starting the Phase 1 plant or selling helium.
The offtake agreement signed in April is a five-year, 100% take-or-pay contract with an investment-grade global industrial gas company for 1.2 million cubic feet a month at a fixed plant gate price of USD 285 per Mcf, with CPI escalation. Management also noted that on October 23 the Department of Energy designated helium a critical material.
The filing states the company generated about USD 17.2 million from Equity sales and issuances in the period, had cash of about USD 2.9 million and USD 11.5 million available under its credit facility at September 30, 2026. Cash used in Operating Activities was USD 4.8 million for the nine months.
Legal Disclosure and Items to Follow
The filing states the company may become party to litigation in the ordinary course of Business and is not currently involved in any proceedings it considers material. The items to follow are EPA approval, Phase 1 execution, remediation cost recovery and cash use.






Please wait processing your request...