Key Highlights

  • Revenue was USD 116 thousand, compared with USD 55 thousand a year earlier.
  • Net loss attributable to common stockholders was USD 20.8 million, or USD 0.07 per share.
  • Binding power purchase agreements total 1,054 megawatts, or about USD 11.9 billion of contracted revenue.
  • Unrestricted cash and cash equivalents were USD 1.9 billion at quarter end.

Fervo Energy Company (NASDAQ:FRVO) reported third quarter 2026 Revenue of USD 116 thousand, compared with USD 55 thousand a year earlier. Net Income was USD 11.7 million, and the net loss attributable to common stockholders was USD 20.8 million, or USD 0.07 per share. Estimates for the quarter stood at EPS of negative USD 0.09 and revenue of USD 135.83 thousand. General and administrative expense was USD 39.35 million, compared with USD 8.12 million.

The company ended the quarter with unrestricted cash and cash equivalents of USD 1.9 billion and current and long-term Debt of USD 301.6 million. It continues to anticipate fourth quarter 2026 revenue in line with prior expectations, which is the first full quarter of revenue from Cape Station.

Cape Station GeoBlock 1

Chief executive Timothy Latimer said the first GeoBlock at Cape Station is the first greenfield enhanced geothermal system development in the world to reach commercial operation, built in 23 months. The company synchronized to the grid on September 24 and declared commercial operation on September 30, ahead of its contractual deadline. GeoBlock 1 is a 33-megawatt plant generating revenue under its PPA, and total installed capacity stands at 36 megawatts.

Management said GeoBlock 1 is performing in line with operational expectations. The trailing 12-month total recordable incident rate is 0.10, and the construction crew reached 1 million hours worked without a recordable incident.

GeoBlock 2 has achieved grid stake, marking the end of hot commissioning, and GeoBlock 3 is in cold commissioning. Commercial operation for both is projected by January 1, 2027, which would complete Cape Station Phase I at approximately 100 megawatts of firm clean power from the first three GeoBlocks. Expected total cost for GeoBlocks 1 through 3 remains approximately USD 7,000 per kilowatt.

Google Agreement and Contracted Backlog

The company signed a 15-year, grid-connected, take-or-pay power purchase agreement with Google covering approximately 396 megawatts in four tranches of 99 megawatts each. Commercial operation is targeted to begin in mid-2028, with all GeoBlocks targeted online before the end of 2028. The company also committed to offer Google an expansion option of approximately 600 megawatts, bringing the total to 1 gigawatt, to be delivered behind the meter under Utah's SB132 framework.

Binding PPAs now total 1,054 megawatts representing approximately USD 11.9 billion of contracted revenue, compared with 658 megawatts at the time of the IPO and an increase of 396 megawatts from last quarter. Of ongoing discussions, approximately 35% are with utilities and load-serving entities, 15% with large load industrial buyers and 50% with data centers and hyperscalers.

GeoBlocks 4 through 11, now called Cape Google 400, consist of eight 50-megawatt units targeted for first power in mid-2028 and approximately 400 megawatts by the end of that year. Drilling for those GeoBlocks is approximately 18% complete with four rigs running. The company states it is positioned to reach USD 5,500 per kilowatt of installed Capital cost for those units, against a long-term target of USD 3,000 per kilowatt.

Resource and Funding Updates

An updated heat-initially-in-place study by an independent consulting firm supports approximately 8.4 gigawatts of capacity potential at Cape Station, compared with a prior estimate of 4.3 gigawatts. The U.S. Department of Energy selected the company for two potential awards totaling approximately USD 20 million, including funding for appraisal wells in Idaho and Nevada. The company's land portfolio spans approximately 670,000 acres.

Dates and Reference Points

The company hosts an investor open house at Cape Station on November 19, 2026. Disclosed reference points include the January 1, 2027 commercial operation date for GeoBlocks 2 and 3, the mid-2028 first power date for Cape Google 400 and the first full quarter of Cape Station revenue in the fourth quarter.