Key Highlights
- Fermi (NASDAQ:FRMI) closed up 13.81% on Thursday, November 12, 2026, after rising as much as 19.89% during the session.
- The company announced agreements with an undisclosed investment-grade hyperscaler for an initial 600 MW at Project Matador beginning in 2027, including a USD 200 million prepayment.
- No definitive Lease is signed yet, and the prior TensorWave lease for 222 MW was terminated.
- Third quarter net loss was USD 141.6 million, and the company remains pre-revenue.
What Fermi Announced
Fermi is developing a large power and Data Center campus called Project Matador. On Thursday it said it had reached agreements with an investment-grade hyperscale customer, which it did not name, to advance an initial 600 MW of power capacity beginning in 2027. The package includes a USD 200 million prepayment, a USD 15 million early construction and site development agreement and a USD 90 million structural steel and building materials purchase agreement that is still being finalized. The parties are working toward a definitive long-term lease, and conditions under the Texas Tech land lease must be satisfied before vertical construction. The stock rose 19.89% at one point and closed up 13.81%. The prepayment is the key element, because it provides customer funding for a project that needs substantial capital. Large technology companies have been competing for sites with access to power, which is the main bottleneck for new AI data centers, so a customer commitment at a power-rich site is valuable. The intraday high of 19.89% and the closing gain of 13.81% show that some buyers took profits as the session progressed.
The Numbers Behind the Story
The company is pre-revenue, and the third quarter showed the cost of building. The net loss was USD 141.6 million, or USD 0.22 per share, compared with USD 346.8 million a year earlier. General and administrative expense was USD 142.2 million, including USD 65.8 million of non-cash Stock Compensation and USD 21.5 million of advisory fees settled in stock. The company spent USD 133.4 million on property and equipment in the quarter and USD 759.5 million in nine months. Debt, net of costs, was USD 958.4 million, up from USD 109.8 million at the end of 2025, and total cash and restricted cash was USD 315.5 million. The company also ended its data center lease and services agreement with TensorWave, signed in August, along with an associated Credit support agreement, which removes a prior customer commitment. The stock-based items are non-cash, but they dilute shareholders, and the increase in Debt means interest costs will rise as construction continues. The company's own description of itself as pre-revenue and pre-lease underlines that the largest value drivers are still ahead.
What Investors Weigh Now
A customer with an investment-grade rating and cash paid in advance reduces financing risk, which explains the jump. But the agreement is not a signed lease, the prepayment is tied to conditions and the Revenue is years away. The company says the project could ramp toward about 17 GW if binding customer agreements follow, a very large figure that depends on permits, power Supply and financing. Management has said that converting its pipeline would Fill the 2.2 GW of current capacity. Investors will watch for the definitive lease, the identity of the customer, financing for construction and the progress on power. Because the company carries debt and burns cash, delays could pressure the stock quickly. Risks include construction cost overruns, equipment delivery times and the possibility that the customer changes its plans, which is why the lease terms are important. The 10-year Treasury Yield near 5.10% also raises the cost of financing, which matters for a developer funding large construction.
Where Things Stand
Fermi gained a hyperscale customer commitment for 600 MW with a USD 200 million prepayment, but a definitive lease remains to be signed. The next milestones are lease execution, construction financing and permits. The company is still pre-revenue with rising debt, so execution is the main risk.