Valor Energy Inc. filed a Form 8-K on October 22, 2026, disclosing that the company entered into the Youngstown Computing Center Equity Transfer Agreement on October 18, 2026, to acquire 100% of the equity interests of Glorious Star LLC, an Ohio limited liability company holding interests in a computing center project in Youngstown, Ohio.

Key Highlights

  • Acquisition target: Glorious Star LLC, which holds interests in a computing center project at 1911 Logan Avenue, Youngstown, Mahoning County, Ohio.
  • Purchase price: The aggregate purchase price for the equity interests is $3,600,000, with a refundable performance deposit of $360,000 due within five business days of the agreement's effective date.
  • Site specifications: According to the filing, the project includes approximately 30,888 square feet of warehouse space and a 23kV electricity connection supplied by Ohio Edison with 18,000 kVA (18 MVA) of site-level apparent power capacity.
  • Land use contract: The filing states the land use contract is valid through December 31, 2030, with renewal in accordance with its terms.
  • Due diligence and closing timeline: The agreement provides for a due diligence period of 30 business days from its effective date, with a closing deadline no later than the 30th business day after that period.
  • Planned use: Following closing, the company disclosed plans to pursue conversion of the project into a data center serving artificial intelligence and high-performance computing workloads.
  • Termination rights: Upon valid termination under Section 5.3 or Section 6.2, the filing states the deposit is refundable in full without interest within five business days, with no break-up fee or liquidated damages obligation.

Valor Energy's Agreement to Acquire Youngstown, Ohio Computing Center Project

Valor Energy Inc. (NASDAQ:VAI) disclosed on October 22, 2026, that it entered into the Youngstown Computing Center Equity Transfer Agreement, dated October 17, 2026, with Glorious Star LLC as both seller and target company. Under the agreement, Valor Energy agreed to acquire 100% of the outstanding equity interests of Glorious Star LLC, which holds interests in a computing center project in Youngstown, Ohio, including site ownership, lease or use and development rights, rights to a 23kV electricity connection, and related equipment, facilities, permits, and contract rights.

The total purchase price is $3,600,000. The filing specifies that within five business days of the agreement's effective date, Valor Energy must place a $360,000 refundable performance deposit into a jointly designated third-party escrow or attorney trust account. At closing, that deposit will be applied toward the purchase price, with the remaining $3,240,000 payable concurrently with the transfer of all equity interests and control of the target company. The company is also required to reimburse the seller $30,000 for remaining prepaid rent through December 31, 2026, payable with the final payment.

The filing notes that although the existing computing center is described as completed and energized, the planned conversion to a data center will require additional design, construction, equipment, and permitting work. The filing also states that "completion of the acquisition and any subsequent development remain subject to significant uncertainties, including satisfaction of closing conditions, verification of available power and usable IT capacity, required approvals and the availability of financing," and that "there can be no assurance that the acquisition or the planned conversion will be completed on the contemplated terms, within the anticipated timeframe or at all." The filing further clarifies that the 18 MVA figure "represents apparent power capacity at the site and does not necessarily equal usable IT load."

What Was Disclosed

Valor Energy Inc. filed an 8-K disclosing entry into an agreement to acquire 100% of Glorious Star LLC's equity interests for $3,600,000, covering a computing center project in Youngstown, Ohio, with plans for conversion into a data center for AI and high-performance computing workloads.