Quanome Technologies, Inc. filed a Form 8-K on October 5, 2026, disclosing two agreements entered on September 29, 2026: a purchase agreement for additional GPU servers and a master services agreement under which its subsidiary will provide AI inference computing capacity.

Key Highlights

  • GPU Server Purchase: Quanome entered Purchase Agreement No. 2 with Compal Electronics, Inc. for 32 GPU server units at an aggregate purchase price of approximately US$18.8 million.
  • Payment Structure: A 20% down payment is required after receipt of the supplier's written order acknowledgment, with the remaining 80% due after shipment readiness confirmation and prior to shipment.
  • AI Services Contract: Subsidiary XDT Infrastructure I, LLC entered a Token Factory Master Services Agreement with XPERT SOFTWARE SOLUTIONS PTE. LTD. for AI inference computing capacity on NVIDIA accelerated computing infrastructure.
  • 60-Month Commitment: The initial order under the services agreement covers a dedicated, physically isolated GPU capacity pool over a 60-month commitment term commencing on service readiness.
  • Aggregate Fees: Committed fees under the initial services order are approximately $100.9 million, payable as a fixed monthly commitment fee that is not reduced for usage below committed levels.
  • Prepayment Terms: A prepayment of approximately $45.0 million is payable in two tranches tied to procurement milestones; as of the filing date, no portion of the prepayment had become due or been paid.
  • Emerging Growth Company: Quanome Technologies is designated an emerging growth company as defined under applicable securities regulations.

Quanome Technologies Discloses GPU Procurement and Long-Term AI Capacity Agreement

According to the filing, Quanome Technologies, Inc. (NASDAQ:QNME) entered two separate agreements on September 29, 2026. The first, Purchase Agreement No. 2, is with Compal Electronics, Inc. for the purchase of 32 GPU server units at an aggregate purchase price of approximately US$18.8 million. The company disclosed that the GPU servers are expected to be delivered to a designated data center location in the United States, and that the agreement includes customary provisions covering delivery, title and risk of loss, inspection and acceptance, warranty coverage, and termination and refund rights in certain circumstances.

The second agreement involves XDT Infrastructure I, LLC, described in the filing as one of the company's indirectly wholly owned subsidiaries. Under the Token Factory Master Services Agreement with XPERT SOFTWARE SOLUTIONS PTE. LTD., XDT will provide AI inference computing capacity hosted on NVIDIA accelerated computing infrastructure. The filing states that aggregate committed fees under the initial order are approximately $100.9 million, with the monthly fee fixed for the 60-month term and not subject to reduction for usage below committed levels. The customer is expected to apply the approximately $45.0 million prepayment substantially toward procurement of the servers and related build-out. The company noted that as of the filing date, no portion of the prepayment had become due or been paid.

The filing notes that completion of the GPU server purchase remains subject to conditions including the company's payment obligations, the supplier's ability to complete production and delivery, applicable product registration and supply-chain requirements, and other customary commercial and operational conditions. The company stated that it intends to file the full texts of both agreements as exhibits to its Quarterly Report on Form 10-Q for the quarter ending September 30, 2026. The filing also contains forward-looking statements, which the company noted are subject to risks and uncertainties and that actual results could differ materially from those anticipated.

What Was Disclosed

Quanome Technologies disclosed two agreements dated September 29, 2026: a GPU server purchase agreement with Compal Electronics for approximately US$18.8 million, and an AI computing capacity services agreement through subsidiary XDT with committed fees of approximately $100.9 million over 60 months.