Osisko Gold approved construction of the Cariboo Gold Project, with a $990 million estimated go-forward Capital obligation and commercial production targeted for H2 2029. The decision matters to investors because the project has up to $1,637 million in available and proposed capital sources, including $837 million in cash and equivalents.

Key Highlights

  • Cariboo project completion stood at 22% as of July 31, 2026, with detailed engineering approximately 40% complete.
  • Osisko Gold Group approved construction of its 100%-owned Cariboo Gold Project with an estimated go-forward capital obligation of $990 million.
  • Trafigura is investing US$30 million through a strategic private Placement and may provide up to US$120 million through a potential prepayment facility.
  • Cariboo was approximately 22% complete as of July 31, 2026, with first gold pour expected in Q1 2029.

Osisko Gold Group Inc. (NYSE: OGG) approved construction of its 100%-owned Cariboo Gold Project, which carries an estimated go-forward capital obligation of $990 million. The project has up to $1,637 million in available and proposed capital sources, including $837 million in cash and equivalents.

Trafigura Financing Supports Cariboo Development

An affiliate of Trafigura is investing US$30 million through a strategic private placement. Trafigura will also take concentrate and doré under offtake agreements, while a potential prepayment Facility could provide up to US$120 million. The project’s construction decision covers the Cariboo development in central British Columbia, Canada.

Engineering and Procurement Advance Toward 2029

Cariboo was approximately 22% complete as of July 31, 2026. Detailed engineering was approximately 40% complete, while procurement and commitments for long-lead items reached approximately 44%, with $325 million committed to date. The first gold pour is expected in Q1 2029, followed by commercial production in H2 2029.