Lithium Americas Corp. filed a current report on November 16, 2026, disclosing that on November 10, 2026, it entered into Omnibus Waiver, Consent and Amendment No. 3 with the U.S. Department of Energy and other parties, amending key agreements governing the DOE loan for Phase 1 of its Thacker Pass project.
Key Highlights
- Third amendment executed: Lithium Americas and its affiliates entered into Omnibus Waiver, Consent and Amendment No. 3 (OWCA 3) with the DOE on November 10, 2026.
- DOE consents to revised project documents: The DOE consented to an amended construction budget, an amended base case financial model, an amended mine plan, and an amended integrated project schedule for Phase 1 of the Thacker Pass project.
- Approximately $650 million in incremental contributions expected: According to the filing, the company expects to provide approximately $650 million of incremental contributions to the LAC-GM Joint Venture from its existing cash and cash equivalents.
- Remaining DOE loan proceeds of approximately $522 million: The company's funding and the remaining approximately $522 million of DOE loan proceeds are expected to be applied toward eligible project costs on a 55.46:44.54 basis, draw-by-draw.
- Up to $127 million additional equity possible: Under OWCA 3, the DOE may, in its sole discretion, require a recalculation of the construction budget and, subject to results, cause up to an additional $127 million of equity contributions to be made by the company to the Borrower.
- GM governance protections established: A separate letter agreement with General Motors Holdings LLC grants GM certain governance rights during a defined Protection Period, including consent rights and the right to appoint at least one voting director, regardless of GM's actual ownership during that period.
- GM top-up option included: Prior to expiration of the Protection Period, GM may elect to make a one-time cash contribution to restore its proportionate interest to ten percent (10%) in the LAC-GM Joint Venture, subject to certain terms and conditions.
Lithium Americas Restructures Thacker Pass Financing with DOE Under OWCA 3
According to the filing, OWCA 3 amends three existing agreements: the Loan Arrangement and Reimbursement Agreement originally dated October 28, 2024 (referred to as the DOE Loan), the Affiliate Support, Share Retention and Subordination Agreement, and the Collateral Agency and Accounts Agreement. The amendment adds a schedule of specified funds to be credited to the Construction Account, replaces the project milestones schedule to reflect the amended integrated project schedule, adds an equity funding schedule setting forth the company's required equity contributions, adds a schedule of deferred plant capital expenditures, and provides for the use of certain funds in specified DOE reserve accounts to pay project costs in accordance with the amended construction budget. The DOE also waived the requirement that a proposed amendment to the construction budget be delivered at least 30 days prior to its adoption, the filing stated.
The filing disclosed that the company expects to provide approximately $650 million of incremental contributions to the LAC-GM Joint Venture from existing cash and cash equivalents. The company's funding and the remaining approximately $522 million of DOE loan proceeds are expected to be applied toward eligible project costs on a 55.46:44.54 basis, draw-by-draw, until both amounts have been fully funded. Additionally, the filing noted that prior to the sixth advance under the DOE Loan, the DOE may in its sole discretion require a recalculation of the construction budget, potentially resulting in up to an additional $127 million of equity contributions by the company.
In connection with OWCA 3, the LAC JV Member, the LAC-GM Joint Venture, and General Motors Holdings LLC entered into a letter agreement on November 10, 2026. The filing stated that under this agreement, GM acknowledges its letters of credit may be drawn in accordance with the DOE Loan, and that neither GM nor its affiliates will be required to reinstate amounts drawn or provide replacement funding. The Protection Period runs from the effective date of the letter agreement until the earlier of GM's first transfer of units to a non-affiliate or the second anniversary of project completion, with a possible extension if GM delivers a "top-up" notice. The company's common shares are listed on the NYSE:LAC and the Toronto Stock Exchange under the symbol LAC.
What Was Disclosed
Lithium Americas Corp. disclosed the execution of OWCA 3 with the DOE on November 10, 2026, amending the DOE Loan and related agreements for Thacker Pass Phase 1, alongside a letter agreement with General Motors Holdings LLC establishing governance protections during a defined Protection Period.