Full House Resorts extended the American Place permanent Facility completion date to February 17, 2029, while allowing the temporary casino structure to continue beyond the permanent opening. The revised agreement matters to investors because it changes the project timetable, phasing, venue plans and the fee structure for the boutique hotel.

Key Highlights

  • The permanent facility is defined as approximately 325,000 square feet.
  • The revised plan includes an approximately 20-room boutique hotel in Phase 1A.
  • A $750.00 per-day fee will apply after Phase 1 begins until the boutique hotel opens.

Full House Resorts Inc. (NASDAQ: FLL) has until February 17, 2029, to complete the permanent American Place casino facility in Waukegan, Illinois. The revised agreement also allows the temporary casino structure to remain in use beyond the permanent property’s opening and updates the project’s development phases. The permanent facility is expected to total approximately 325,000 square feet across Phase 1 and Phase 1A. Phase 1A includes an approximately 20-room boutique hotel, while the entertainment venue may use all or part of the temporary facility for performances, meetings, assemblies and special events capable of accommodating approximately 1,500 attendees. The development property includes an approximately 31.7-acre city-owned parcel at 600 Lakehurst Road and parcels at 4001-4011 Fountain Square Place. The agreement also revises project sequencing and future-phase details to match current design plans.

Boutique Hotel Fee Replaces Other Timing Remedies

After Phase 1 begins operations, FHR-Illinois LLC will owe the City of Waukegan a $750.00 per-day late opening fee until the boutique hotel begins operations. The fee is payable monthly in arrears and ends permanently when the hotel opens. The agreement makes that payment the City’s exclusive remedy for timing, construction, completion or operation issues involving the boutique hotel.