Fervo Energy Company filed a Form 8-K on September 1, 2026, disclosing that its wholly owned subsidiary Cape Generating Station 6 LLC entered into a Power Purchase Agreement with Google Energy LLC on August 26, 2026, for the sale of energy from a 396 MW enhanced geothermal systems project in Beaver County, Utah.
Key Highlights
- Project size: The PPA covers a 396 MW enhanced geothermal systems project located at Cape Station in Beaver County, Utah.
- Delivery structure: The project will be delivered in four successive 99 MW sub-tranches, with target commercial operation dates beginning in the third quarter of 2028.
- Contract length: The PPA carries a 15-year delivery term.
- Capacity expansion option: Fervo has agreed to offer Google an option for approximately 600 MW of additional capacity at Cape Station, which would bring total contracted enhanced geothermal capacity to not less than approximately 950 MW, with a guaranteed commercial operation date no later than June 2030.
- Parent guaranties: Fervo Energy Company has provided a parent company guaranty for CGS 6's obligations, and Alphabet Inc. has provided a parent company guaranty for Google's obligations under the PPA.
- Reimbursement risk: If Fervo does not make the required capacity expansion offer, it is obligated to reimburse Google for amounts previously paid in respect of deemed delivered energy; the filing states this amount "is not currently estimable."
- Regulatory dependency: The project is intended to utilize flexible power delivery pathways under Utah Senate Bill 132 but "remains subject to receiving relevant regulatory approvals required under SB 132," according to the filing.
Fervo and Google Structure a Phased Geothermal Supply Agreement at Cape Station
According to the filing, Cape Generating Station 6 LLC, a wholly owned subsidiary of Fervo Energy Company (NASDAQ:FRVO), executed the PPA with Google Energy LLC, a subsidiary of Alphabet Inc. The agreement covers energy products from an enhanced geothermal systems project at Cape Station. Fervo reported that the project's 396 MW nameplate capacity will be developed in four equal sub-tranches of 99 MW each, with commercial operations targeted to begin in the third quarter of 2028 and the 15-year delivery term running from that point.
The filing also discloses a capacity expansion component. Fervo has agreed to offer Google an option for approximately 600 MW of additional capacity at Cape Station, which, combined with the 396 MW PPA, would result in total contracted enhanced geothermal capacity of not less than approximately 950 MW. Any expansion remains contingent on Google's acceptance and the negotiation of a mutually acceptable definitive agreement. The filing notes that if Fervo fails to make the required expansion offer, it must reimburse Google for deemed delivered energy payments already made, based on the difference between the market price and the PPA price at the time the obligation arises.
The project's delivery structure is described as intended to operate under Utah Senate Bill 132, which the filing states authorizes flexible power delivery pathways. Under that framework, the filing anticipates that Fervo's enhanced geothermal systems, supplemented by additional energy resources, would deliver capacity through a closed private generation system that may be configured for either front-of-the-meter or behind-the-meter interconnection to serve data center load. Fervo stated it anticipates target commercial operation for this expanded delivery capability in the first half of 2030, subject to further engineering feasibility and agency approvals. The filing was signed by David Ulrey, Chief Financial Officer.
What Was Disclosed
Fervo Energy disclosed a 15-year, 396 MW Power Purchase Agreement with Google Energy LLC for enhanced geothermal energy from Cape Station in Utah, along with an option for Fervo to offer approximately 600 MW of additional capacity, contingent on regulatory approvals and mutual agreement.