Ellomay Capital Ltd. filed a Form 6-K on September 29, 2026, announcing that its subsidiary Ellomay Solar received a grid access and connection permit for a 22.2 MW / 100.3 MWh battery storage project.
Key Highlights
- Permit received: Ellomay Solar obtained a grid access and connection permit, according to the filing.
- Project capacity: The battery storage system is rated at 22.2 MW / 100.3 MWh with a 4.5-hour storage duration, as described in the press release title incorporated by reference.
- Filing date: The report was signed and submitted on September 29, 2026, for the month of September 2026.
- Incorporated by reference: Paragraphs 1-2 of Exhibit 99.1 are incorporated by reference into the registrant's registration statements on Form F-3 (Nos. 333-199696 and 333-144171) and Form S-8 (Nos. 333-187533, 333-102288, and 333-92491).
- Signatory: The report was signed by Ran Fridrich, Chief Executive Officer and Director of Ellomay Capital Ltd.
Ellomay Solar Battery Storage Permit: Details From the September 2026 Filing
Ellomay Capital Ltd., an Israeli company headquartered at 18 Rothschild Blvd., Tel Aviv, Israel, submitted a Report of Foreign Private Issuer on Form 6-K for the month of September 2026, under Commission File Number 001-35284. The filing incorporates by reference a press release dated September 29, 2026, titled "Ellomay Announces Receipt of a 22.2 MW / 100.3 MWh (4.5-hour) Battery Storage Grid Access and Connection Permit by Ellomay Solar."
According to the filing, the grid access and connection permit covers a battery storage system with a capacity of 22.2 MW and 100.3 MWh, representing a 4.5-hour storage duration, received by Ellomay Solar. The filing does not provide additional operational or financial details beyond the permit announcement within the text submitted to the SEC; the full substantive disclosure is contained in Exhibit 99.1, paragraphs 1-2 of which are incorporated by reference into the company's existing registration statements on Form F-3 and Form S-8, as listed in the filing.
The registrant files its annual reports under cover of Form 20-F, as indicated on the form. The report was duly authorized and signed by Ran Fridrich in his capacity as Chief Executive Officer and Director on September 29, 2026.
What Was Disclosed
Ellomay Capital Ltd. disclosed via a Form 6-K that its subsidiary Ellomay Solar received a grid access and connection permit for a 22.2 MW / 100.3 MWh (4.5-hour) battery storage project, with the announcement dated September 29, 2026.