BKV Corporation filed a current report on October 7, 2026, disclosing that a wholly owned subsidiary entered into an equipment supply contract on October 2, 2026, with a Tier 1 supplier for approximately $800.0 million in power generation equipment intended for a prospective Texas power project.

Key Highlights

  • Contract value: The aggregate purchase price under the Supply Contract is approximately $800.0 million.
  • Equipment scope: The Supply Contract covers two turbines, certain balance of plant equipment, and related services.
  • Delivery window: The Supplier is to supply and deliver the Equipment between September 2028 and May 2029.
  • Reservation fee credit: $80.0 million in reservation fees previously paid by the Company are credited against the Contract Price.
  • Near-term payment milestone: Approximately $200.0 million of the Contract Price (inclusive of the $80.0 million credit) is due on or before March 31, 2027.
  • Hyperscaler backstop: Approximately 90% of the portion of the Contract Price due on or before March 31, 2027 is covered by a backstop agreement with a leading investment grade hyperscaler, which is also the intended offtaker for the project.
  • Termination right: If mutually agreeable offtake arrangements have not been reached by March 31, 2027, BKV may terminate the Supply Contract for convenience with no further payment obligations.

BKV's Equipment Supply Contract for Its Prospective Texas Power Generation Project

According to the filing, a wholly owned subsidiary of BKV Corporation (NYSE:BKV) entered into the Supply Contract on October 2, 2026, with an unnamed Tier 1 supplier. The Equipment to be purchased includes two turbines, certain balance of plant equipment, and related services, all intended for the Company's prospective power generation project in Texas. The Supplier is contracted to deliver the Equipment between September 2028 and May 2029, with installment payments on the remaining Contract Price running from October 2026 through December 2028.

The filing notes that $80.0 million in reservation fees already paid by the Company are credited against the $800.0 million Contract Price. Of the total amount, approximately $200.0 million is due on or before March 31, 2027. The filing further discloses that approximately 90% of that near-term payment obligation is backed by a "backstop agreement with a leading investment grade hyperscaler," which the Company identifies as the intended offtaker for the project.

The filing includes a termination provision: if BKV and the hyperscaler have not reached mutually agreeable offtake arrangements by March 31, 2027, "BKV may at such time terminate the Supply Contract for convenience and have no further payment obligations thereunder." The filing states that the full text of the Supply Contract will be filed as an exhibit to BKV's Annual Report on Form 10-K for the fiscal year ending December 31, 2026. The filing was signed by David R. Tameron, Chief Financial Officer, and contains forward-looking statements that, according to the filing, are subject to risks and uncertainties described in BKV's regulatory filings.

What Was Disclosed

BKV Corporation disclosed an equipment supply contract valued at approximately $800.0 million for two turbines and related equipment for a prospective Texas power project, including payment terms, a hyperscaler backstop arrangement, and a conditional termination right tied to a March 31, 2027 offtake deadline.