Allied Gold Corp has energized the Kurmuk Mine’s connection to Ethiopia’s national electrical grid as first ore moves through the commissioned crushing circuit. The milestones advance commissioning toward operations and are expected to support significant growth in gold production and cash flows as the mine ramps up.

Key Highlights

  • First ore reached Kurmuk’s commissioned crushing circuit earlier this month.
  • Mining activity continues to advance as planned at the Ethiopian mine.
  • Allied Gold’s Kurmuk Mine in Ethiopia completed and energized its connection to the national electrical grid.

Allied Gold Corp (NYSE: AAUC) is a precious metals company. Its Kurmuk Mine in Ethiopia has completed and energized its connection to the national electrical grid.

Kurmuk Mine Builds Toward Plant Ramp-Up

Ore stockpiles are building to support plant feed during the ramp-up to commercial production. The company’s update covers the mine’s operational readiness as it advances from commissioning toward production. Kurmuk is expected to become one of Allied Gold’s premier gold mines.

Remaining Commissioning Work Carries Key Conditions

The transition depends on completing the remaining commissioning and Utility work on time and receiving required approvals. Plant performance, availability and recovery are expected to remain consistent with the mine plan, while personnel, contractors, equipment, consumables and funding must be available.